ST. JOSEPH, Mo. – P1 Group, Inc. is pleased to announce it has won the mechanical, plumbing and low-purity process piping work on a project for Boehringer Ingelheim Vetmedica, Inc. (BIVI) in St. Joseph, Mo. The project consists of a new drug production facility and a new administrative building.
This project was awarded in February 2010 and is expected to be completed by February 2012.
Scope of Work
- Chilled water
- Tower water
- 120# steam
- Clean compressed air
- Compressed air
- Several gases (oxygen, nitrogen, carbon dioxide, etc.)
Congratulations to the following associates who were integral in securing this work for P1 Group:
- Jerry Phillips, Chief Mechanical Estimator
- Jeff Peterson, Estimator
- Dean Baird, Project Manager
- Joe Camren, Project Manager
Boehringer Ingelheim Vetmedica, Inc. produces animal health products and is a subsidiary of Boehringer Ingelheim Corporation.